MBR vs MBBR for a sewage treatment plant: lifecycle cost and where each fits

3 days ago
4 min read

Updated: 8 hours ago

At a glance: an MBBR plant costs less to build and uses less electricity, but its effluent needs a clarifier, a sand or disc filter and disinfection before it can be reused, and even then it is not what an MBR gives. An MBR costs more to build, uses more air and has a membrane replacement line, but it makes clear, disinfected water in about half the footprint and is what most reuse specifications now call for. Over ten years the two are closer than their capital costs suggest, and the deciding factor is usually what the treated water is worth and how much land there is.

What each process does


MBBR

MBR

Biology

Biofilm on plastic carriers in an aerated tank

Suspended growth at 8 to 12 g/L MLSS

Solids separation

Clarifier, then tertiary filter

Hollow fibre or flat sheet membrane, 0.04 to 0.1 µm

Effluent

BOD 10 to 20 mg/L, TSS 10 to 30 mg/L after the clarifier; better after filtration

BOD below 5 mg/L, TSS below 1 mg/L, turbidity below 1 NTU, bacteria largely removed

Footprint

Tank, clarifier, filter and disinfection

About half, no clarifier or filter

Sludge

More, and it settles in a clarifier

Less, from the longer sludge age

Sensitivity

Tolerates shocks; carriers can wash out

Needs fine screening and flux discipline

Operator skill

Lower

Higher: cleaning, integrity checks

Capital cost

For the same flow, an MBR's civil work is smaller but it buys membranes, cassettes, scour blowers and a fine screen that the MBBR does not need. An MBBR buys carriers, a clarifier and, if the water is to be reused, a filter and a chlorination or UV step. In India the two capital costs end up in the same range once the MBBR carries its tertiary stage; without tertiary treatment the MBBR is clearly cheaper, but then it is not making the same water.

Running cost on a 2 MLD plant

The MBR side is the Compass design in MBR membrane replacement cost: 160 TW-MBR-40 modules, 0.79 kWh/m³. The MBBR side uses typical published figures for a plant with a clarifier, disc filtration and chlorination.

Line, ₹ per m³

MBBR with tertiary

MBR

Electricity at ₹8/kWh

3.2 to 4.8 (0.4 to 0.6 kWh/m³)

6.3 (0.79 kWh/m³)

Chemicals

0.3 to 0.6 (coagulant, chlorine)

0.4 (hypochlorite, citric acid)

Membranes

none

3.1 at ₹1 lakh a 40 m² module over 7 years

Carrier and filter media replacement

0.2 to 0.5

none

Sludge handling

higher

lower

Total before labour

about 4 to 6

about 10

So the MBR costs roughly ₹4 to ₹6 more per m³ to run, or ₹30 to ₹45 lakh a year on 2 MLD. That is the number to set against the value of the water and the land.

Where the money comes back

  • Reuse. MBR permeate goes straight to cooling towers, flushing, horticulture or to an RO plant for process water. Where reuse water replaces purchased water at ₹30 to ₹60 per m³, the MBR's extra running cost is covered many times over; an MBBR needs a filter and disinfection to reach the same uses, and still gives RO pretreatment a harder time.

  • Land. An MBR saves the clarifier and filter area. On an industrial site or a township where land is priced, the saving is often larger than the whole membrane budget.

  • Discharge limits. Where the consent asks for BOD below 10 mg/L and TSS below 10 mg/L, an MBR meets it without a tertiary stage; an MBBR needs one, and its filter is another thing to run.

  • Upgrades. An existing activated sludge or MBBR plant can be converted to MBR in its own tanks to double its capacity without new civil work; see MBR for Jal Jeevan Mission and AMRUT upgrades.

Ten-year view

Taking the 2 MLD plant, the MBR's extra running cost over ten years is about ₹3 to ₹4.5 crore, of which the membranes are about ₹2.3 crore at the price assumed. Against that: the land saved, the tertiary stage not built or run, the sludge not handled, and the water reused. On a greenfield STP with no reuse and cheap land, MBBR wins. On a site that reuses its water, is short of land or has a tight discharge consent, MBR wins, and the margin grows as the membrane price falls.

Where each fits

  • MBBR: small to medium STPs with discharge to a sewer or river, room for a clarifier, no reuse, and limited operating skill on site.

  • MBR: reuse of any kind, industrial sites, townships and hospitals short of land, upgrades inside existing tanks, and anywhere the consent is tight.

  • Either: where land and reuse are not pressing, the decision is the membrane price against the tertiary stage; ask for both quotations with their running costs, not only their capital costs.

Every figure in this article comes from Theway Compass, Theway's free online design tool. Open it, enter your own flow, water and prices, and it gives the same tables for your plant.

Questions

Is MBR energy always higher? Yes, by about 0.2 to 0.4 kWh/m³, almost all of it membrane scour air. Newer module designs and intermittent scour narrow the gap.

Can MBBR effluent be reused? For flushing and horticulture after filtration and disinfection, yes. For cooling towers and RO feed it needs more treatment, and the filter is usually an ultrafiltration unit, at which point the cost comparison with MBR changes.

What about SBR? Much the same conclusions as MBBR: lower cost, larger footprint, tertiary treatment for reuse.

Send your plant details to mail@thewaymembranes.com or use the enquiry form for a quotation and a reviewed design.

Specification note. Typical values only. They depend on feed water, system design and operation in line with the Theway operation manual, and may change without notice. Prices in this article are assumptions for illustration, not Theway's prices; ask Theway for a current quotation.

Specification note: figures are typical values for information only and are not a performance guarantee. Actual performance depends on the feed water, pretreatment and operation. See the product and datasheet disclaimer.