MBR membrane replacement cost: how to estimate it for your STP

3 days ago
5 min read

Updated: 11 hours ago

At a glance: an MBR sewage plant needs roughly 3,000 m² of membrane per MLD of average flow when it is designed for a peak flux of about 20 L/m²·h. Its replacement cost per m³ is that area, times the price per m², divided by the years the membranes last and the water treated in a year. For the 2 MLD example below, every ₹1 lakh a 40 m² module costs adds about ₹3 per m³ over a seven-year life. Electricity, mostly aeration, is the larger running cost at about ₹6 per m³, and chemicals are under ₹0.50. The figures come from Theway Compass, where you can run your own plant.

Start with the membrane area

MBR membranes are sized on the peak flow, not the average, because the membrane has to pass whatever arrives. The design flux is low, 15 to 25 L/m²·h for municipal sewage, so that the membrane can be relaxed and backwashed without falling behind.

Item

Value

Average flow

2,000 m³/day (2 MLD)

Peak factor

1.5, so 125 m³/h at peak

Design flux at peak

20 L/m²·h at 25 °C

Membrane area required

5,620 m² for the peak, 4,690 m² on average flow

Module


TW-MBR-40, 40 m² reinforced PVDF hollow fibre, 0.04 µm

Installed

160 modules in 8 cassettes of 20, two trains of 4 cassettes; 6,400 m²

Flux in service

14.6 L/m²·h on average flow, 22 at peak

Mixed liquor

10 g/L in the membrane tank, 8 g/L in aeration

The installed area is 14 % more than the peak requirement because cassettes come in whole numbers of modules and a plant should keep running with one train out for a recovery clean. That gives the rule of thumb: about 3,200 m² installed per MLD at these conditions, less if the peak factor is lower or the sewage warmer.

The replacement cost formula

Replacement cost per m³ = (modules × price per module) ÷ (membrane life in years × water treated per year).

This plant treats 730,000 m³ a year with 160 modules. For every ₹1 lakh a module costs, the set costs ₹1.6 crore and:

Membrane life

Replacement cost per m³, per ₹1 lakh a module

Per MLD per year

5 years

₹4.38

₹16 lakh

7 years

₹3.13

₹11.4 lakh

10 years

₹2.19

₹8 lakh

Quotations are easier to compare per square metre than per module, because module sizes differ between makes: ₹1 lakh for a 40 m² module is ₹2,500 per m² (illustrative figures, not a Theway price). Ask every supplier for the price per m², the guaranteed life and the conditions attached to it, and put all three into the formula.

What is replaced, and what is not

  • Modules, not cassettes. In a well-designed plant the cassette frame, the permeate headers and the air scour piping stay for the life of the plant; only the membrane modules are changed. Theway modules are made to fit the cassettes of the common makes, so the frame and pipework stay; see replacing submerged MBR modules by brand.

  • Part of the plant at a time. Modules rarely all fail at once. A plant with two trains can change one train in a year and the other the next, which halves the cash in any one year and lets the new modules be compared with the old under the same sewage.

  • Blowers and pumps. These last longer than membranes and are not part of the membrane cost, but their energy is the largest running cost of all, below.

The other running costs, for scale

Compass gives the full operating picture of the same plant, at ₹8 per kWh and the chemical prices shown:

Line

Basis

₹ per m³

Process air blowers

22.9 kW for the biological oxygen demand

2.20

Membrane scour blowers

36.4 kW, 1,760 Nm³/h of coarse bubble air

3.49

Permeate, recirculation pumps and mixers

6.2 kW

0.60

Electricity total

0.79 kWh/m³

6.29

Sodium hypochlorite, maintenance cleans twice a week

200 mg/L, 10.6 tonnes a year as 100 %, ₹150/kg

0.27

Hypochlorite and citric acid, recovery cleans twice a year

2,000 mg/L and 0.5 %

0.13

Membranes, ₹1 lakh a module over 7 years

160 modules

3.13

Total before sludge handling, labour and maintenance


about 9.8

Membrane air scour is the single largest line, and it is where module design matters most: a module that holds its flux with less air pays for itself in electricity before its price is counted. Theway's reinforced fibres are run at the scour rates in the operation manual; running more air than the manual asks for costs money without extending life.

What makes membranes last

  • Flux discipline. Running above the design flux to take a peak the plant was not sized for is the quickest way to lose a year of life.

  • Mixed liquor. MLSS above about 10 g/L in the membrane tank raises the viscosity and the fouling rate; Compass lowers the design flux to allow for it.

  • Screening. Fine screens of 1 to 2 mm ahead of the biology keep hair and fibre off the membranes; most early failures trace back to a screen.

  • Cleaning. Maintenance cleans with hypochlorite twice a week and recovery cleans twice a year, within the chlorine limits of the membrane; see membrane cleaning limits.

  • Reinforcement. A braid-reinforced fibre survives the scour and the occasional dewatered tank that would break a plain fibre.

Every figure in this article comes from Theway Compass, Theway's free online design tool. Open it, enter your own flow, water and prices, and it gives the same tables for your plant.

Questions

How much membrane area per MLD? About 2,800 to 3,200 m² installed per MLD of average flow for municipal sewage at a peak factor of 1.5 and 20 L/m²·h; more for cold sewage or higher peaks.

How long do MBR membranes last? Five to ten years in municipal service when the plant is screened, cleaned and run within its limits; shorter in industrial effluent with oil, solvents or wide pH swings.

Is the replacement cost the biggest cost? Usually not: aeration electricity is larger in most Indian STPs at current tariffs. Membrane cost matters most where the tariff is low or the membranes are imported.

Can I compare this with an MBBR plant? Yes; see MBR vs MBBR for an STP: lifecycle cost.

Send your plant details to mail@thewaymembranes.com or use the enquiry form for a quotation and a reviewed design.

Specification note. Typical values only. They depend on feed water, system design and operation in line with the Theway operation manual, and may change without notice. Prices in this article are assumptions for illustration, not Theway's prices; ask Theway for a current quotation.

Specification note: figures are typical values for information only and are not a performance guarantee. Actual performance depends on the feed water, pretreatment and operation. See the product and datasheet disclaimer.