Commissioning new UF modules: a start-up checklist
At a glance: commission new UF modules in this order: flush the pipework before the modules go in, check instruments and valves, fill slowly and vent all air, flush the preservative to drain, start at low flux and ramp up, set backwash and flush cycles inside the datasheet ranges, run an integrity check and record a day-one baseline of flow, TMP and temperature.

Before the modules go in
Flush all pipework. Weld spatter, PVC shavings and sand from construction will damage fibres. Flush headers and lines to drain until the water runs clear.
Check the screen. A fine self-cleaning screen should sit ahead of the UF. Ask us for the screen rating for your module and feed.
Check instruments. Pressure gauges or transmitters on feed, concentrate and filtrate; flow meters on feed and filtrate; a temperature reading on the feed.
Check valves and pumps for surge. Fast-closing valves and pumps that start at full speed cause water hammer, which breaks fibres. Use slow-acting valves and soft starters or VFDs. See water hammer in UF membranes and part 2.
Start-up steps
Step | What to do | Limit to respect |
|---|---|---|
1. Install | Fit modules with new seals; do not let fibres dry out | Keep modules wet once opened |
2. Fill and vent | Fill at low flow with the vent open until no air comes out | Feed pressure well below 3 kg/cm² |
3. Flush preservative | Run filtrate and concentrate to drain until foaming stops and the filtrate is clear | Do not send flush water to RO |
4. First backwash | Run a backwash at low flux and check every module vents and drains | Backwash pressure below 2 kg/cm² |
5. Ramp flux | Start at about half the design flux and increase in steps over the first days | TMP below 1 kg/cm² |
6. Set cycles | Filtration 15 to 60 min, backwash 20 to 60 s, flush 20 to 60 s, then adjust from data | Datasheet ranges |
7. Integrity check | Run a pressure decay or bubble test on each train | Filtrate turbidity steady and low |
8. Baseline | Record flow, feed, concentrate and filtrate pressure and temperature | Repeat daily |
Limits are from Theway Stream and retrofit datasheets. Pressure limits fall at higher temperatures; use the derating table on the module page.
The day-one baseline
Every later decision, from cleaning to troubleshooting, compares today's reading with the clean baseline. Record:
filtrate flow and feed flow
feed, concentrate and filtrate pressure, and TMP
feed temperature
filtrate turbidity
backwash pressure and flow
Normalise to a reference temperature (20 or 25 °C) so seasonal changes do not look like fouling. See transmembrane pressure explained.
Checklist
Pipework flushed before installation
Screen in place and clean
Instruments calibrated
Valves slow-acting, pumps soft-started
Air vented on fill
Preservative flushed to drain
Flux ramped, not stepped to full
Cycles set within datasheet ranges
Integrity check passed
Baseline logged
Questions buyers ask
How long should I flush the preservative?
Until the filtrate no longer foams and its quality is steady. Send it to drain, not to RO or storage.
Can I start at full flow?
No. Ramp up over the first days. New fibres settle and the cake layer forms gradually.
What if one train shows a much lower TMP than the others?
Check for a bypass or a damaged seal first, then run an integrity test.
Do you support commissioning?
Yes. Ask about commissioning support when you order.