Commissioning new UF modules: a start-up checklist

Nov 12
3 min read

At a glance: commission new UF modules in this order: flush the pipework before the modules go in, check instruments and valves, fill slowly and vent all air, flush the preservative to drain, start at low flux and ramp up, set backwash and flush cycles inside the datasheet ranges, run an integrity check and record a day-one baseline of flow, TMP and temperature.

Commissioning new UF modules: a start-up checklist

Before the modules go in

  • Flush all pipework. Weld spatter, PVC shavings and sand from construction will damage fibres. Flush headers and lines to drain until the water runs clear.

  • Check the screen. A fine self-cleaning screen should sit ahead of the UF. Ask us for the screen rating for your module and feed.

  • Check instruments. Pressure gauges or transmitters on feed, concentrate and filtrate; flow meters on feed and filtrate; a temperature reading on the feed.

  • Check valves and pumps for surge. Fast-closing valves and pumps that start at full speed cause water hammer, which breaks fibres. Use slow-acting valves and soft starters or VFDs. See water hammer in UF membranes and part 2.

Start-up steps

Step

What to do

Limit to respect

1. Install

Fit modules with new seals; do not let fibres dry out

Keep modules wet once opened

2. Fill and vent

Fill at low flow with the vent open until no air comes out

Feed pressure well below 3 kg/cm²

3. Flush preservative

Run filtrate and concentrate to drain until foaming stops and the filtrate is clear

Do not send flush water to RO

4. First backwash

Run a backwash at low flux and check every module vents and drains

Backwash pressure below 2 kg/cm²

5. Ramp flux

Start at about half the design flux and increase in steps over the first days

TMP below 1 kg/cm²

6. Set cycles

Filtration 15 to 60 min, backwash 20 to 60 s, flush 20 to 60 s, then adjust from data

Datasheet ranges

7. Integrity check

Run a pressure decay or bubble test on each train

Filtrate turbidity steady and low

8. Baseline

Record flow, feed, concentrate and filtrate pressure and temperature

Repeat daily

Limits are from Theway Stream and retrofit datasheets. Pressure limits fall at higher temperatures; use the derating table on the module page.

The day-one baseline

Every later decision, from cleaning to troubleshooting, compares today's reading with the clean baseline. Record:

  • filtrate flow and feed flow

  • feed, concentrate and filtrate pressure, and TMP

  • feed temperature

  • filtrate turbidity

  • backwash pressure and flow

Normalise to a reference temperature (20 or 25 °C) so seasonal changes do not look like fouling. See transmembrane pressure explained.

Checklist

  • Pipework flushed before installation

  • Screen in place and clean

  • Instruments calibrated

  • Valves slow-acting, pumps soft-started

  • Air vented on fill

  • Preservative flushed to drain

  • Flux ramped, not stepped to full

  • Cycles set within datasheet ranges

  • Integrity check passed

  • Baseline logged

Questions buyers ask

How long should I flush the preservative?

Until the filtrate no longer foams and its quality is steady. Send it to drain, not to RO or storage.

Can I start at full flow?

No. Ramp up over the first days. New fibres settle and the cake layer forms gradually.

What if one train shows a much lower TMP than the others?

Check for a bypass or a damaged seal first, then run an integrity test.

Do you support commissioning?

Yes. Ask about commissioning support when you order.