Upgrading an existing STP to MBR
Updated: 11 hours ago
At a glance: converting an existing STP to a membrane bioreactor (MBR) replaces the secondary clarifier and tertiary filters with membranes submerged in the biological process. Because MBR runs at higher mixed liquor solids, the same tanks can often treat more sewage, and the permeate is suitable for reuse. The conversion needs fine screening, a membrane tank or zone, scour aeration, permeate pumps and a cleaning system.

When an upgrade makes sense
the plant is overloaded and there is no space to extend
discharge or reuse norms have tightened beyond what clarifier and filters deliver
the secondary clarifier is a frequent source of problems
the owner wants reuse water without adding a separate tertiary plant
The conversion step by step
Audit. Measure real flows and loads, including peaks, and survey tank volumes and condition.
Screening. Install fine screening. Hair and fibres are the main threat to MBR membranes.
Membrane tank. Convert part of the aeration tank or the old clarifier into a membrane zone, with recirculation back to the biological tank.
Aeration. Add scour blowers and diffusers under the membranes, separate from process aeration.
Permeate system. Permeate pumps, a vacuum or pressure transmitter for TMP, and flow measurement.
Cleaning. A chemical dosing and cleaning-in-place system for hypochlorite and acid.
Controls. Automatic cycles for filtration, relaxation or backwash, and cleaning.
Commissioning. Raise mixed liquor solids gradually and bring membranes online in stages.
Choosing membranes
Option | Best for |
|---|---|
Flat sheet cassettes, 15 to 500 KLD | Smaller plants, easy inspection, MLSS up to 18,000 mg/L |
Tight tank volume, automated backwash | |
Large plants and replacing ZeeWeed 500D modules |
Common pitfalls
Weak screening, leading to ragging and sludging of modules
Underestimating peak flow, forcing high flux at peak hours
Scour aeration designed as an afterthought
No space or access to lift membranes for inspection
Operators not trained on the cleaning routine
Checklist
Flow and load audit
Fine screen specified
Membrane zone and recirculation designed
Scour and process aeration separated
Permeate, instrumentation and cleaning systems included
Lifting access for modules
Operator training planned
Questions buyers ask
How much more capacity can an MBR upgrade give?
It depends on the existing tanks and loads. The audit decides it; we size from your data.
Can the plant keep running during conversion?
Usually, if the work is phased by tank or train. Plan it with the contractor.
Does MBR permeate meet reuse norms?
MBR permeate is low in suspended solids and bacteria and suits most non-potable reuse. See CPHEEO guidelines and MBR.
Plan your upgrade